STAGE 05 OF 08
MEP Engineering
18 to 28 Days
Smart MEP & Services Routing
"Intelligent mechanical, electrical, and plumbing conduit routing with zero clash."
3D BIM spatial coordination of electrical circuits, 3-phase power distribution, sanitary drainage falls, water supply pressure lines, and HVAC ducts.
Why This Stage Matters:Post-construction chasing of walls to fix plumbing leaks or missed electrical points ruins finishes and weakens masonry. Pre-planned 3D MEP eliminates rework.

SIID Technical Intelligence
Verified Engineering Milestone • Stage 05
Real-World Implementation Case Study
Aura Smart Residence (G+2 Smart Home with Home Automation)
Traditional / Unverified Baseline
Conventional manual MEP installation resulting in 18 structural beam puncture clashes and inadequate EV charger wiring.
SIID Intelligent Outcome
Zero structural penetrations using designated pre-cast slab sleeves, concealed CAT6 + KNX automation conduits, and 100% leak-proof CPVC lines.
Key Engineering Milestones Achieved:
Eliminated 14 potential beam clashes during 3D simulation before masonry commenced.
Hydrostatic pressure tested to 10 kg/cm² for 24 hours with zero pressure drop.
Balanced 3-phase load to within 4.5% variance across all R-Y-B phases.
Connected Electrical Load
18.5 kW (3-Phase 415V)
Earth Resistance Reading
0.78 Ohms (Safe < 1.0)
Plumbing Pressure Test
10 Bar sustained 24 hrs
Drainage Fall Gradient
1:40 (25mm per 1m run)
Key Stakeholders Involved
MEP Consultant
Licensed Electrical Contractor
Plumbing Specialist
Home Automation Engineer
Estimated Schedule
18 to 28 Days
Standard execution timeline based on automated SIID workflow sequencing and verified contractors.