STAGE 03 OF 08
Cost & Approvals
12 to 20 Days
Approvals & Deterministic BOQ
"Secure municipal building permits and lock in itemized material quantity pricing."
Automated municipal drawing production, statutory authority sanctions, and bill of quantities computed down to every steel bar and cement bag.
Why This Stage Matters:Unplanned material escalation causes 70% of project budget overruns. A deterministic BOQ gives absolute financial clarity before groundbreaking.

SIID Technical Intelligence
Verified Engineering Milestone • Stage 03
Real-World Implementation Case Study
Greenwood Villa (G+2 Residential (3,600 sq.ft))
Traditional / Unverified Baseline
Estimated project budget between ₹75L - ₹95L with undefined cost escalation buffer.
SIID Intelligent Outcome
Fixed deterministic BOQ of ₹78.42 Lakhs with locked material pricing and GHMC building permit cleared in 14 days.
Key Engineering Milestones Achieved:
Quantified exact requirement: 1,420 cement bags and 11.2 Tons of Fe 550D TMT steel.
Saved ₹3.4 Lakhs by bulk-contracting steel at pre-escalation quarterly pricing.
Zero municipal rejection queries due to auto-checked setback code rules.
Total Estimated Civil Cost
₹46.20 Lakhs
Finishes & MEP Budget
₹32.22 Lakhs
Steel Consumption Rate
3.85 kg / sq.ft
Cement Consumption Rate
0.39 bags / sq.ft
Key Stakeholders Involved
Licensed Municipal Liaison Architect
Quantity Surveyor (QS)
Civil Contractor
Structural Engineer
Estimated Schedule
12 to 20 Days
Standard execution timeline based on automated SIID workflow sequencing and verified contractors.